Modular containers on Mount Snowdon
Reparations to Mount Snowdon pipeline works supported by temporary units provided by Algeco.
Contents |
[edit] Brief
Snowdon or Yr Wyddfa, is the highest mountain in Wales, at an elevation of 1,085 metres above sea level, and the highest point in the British Isles outside the Scottish Highlands. Located in Snowdonia National Park in Gwynedd, the mountain is also home to the Cwm Dyli hydro-electric power station, owned by RWE Renewables.
The concrete structures supporting the pipeline that runs down the side of Mount Snowdon feeding the power station are relatively old, and so needed to be replaced. Jennings Building & Civil Engineering Ltd were appointed by RWE to carry out the maintenance.
[edit] Solution
Due to the particularly dangerous location of the project, Jennings needed to ensure that their employees’ safety and welfare was of top priority. They selected Algeco to provide modular accommodation to the site, due to our reputation for health and safety, reliability and high quality products.
The mountainous location of the site meant that any accommodation would need to be transported by helicopter, so Algeco needed to select a lightweight solution that met the weight restrictions (1200kg).
Algeco’s storage containers were under this weight, and the company’s Deeside depot changed them all into small canteens (added a sink, worktop, electrics and lighting). However, due to the weight restrictions, the sink and worktops couldn’t be fitted until the storage containers were on the mountain as the furniture would have made the containers too heavy.
[edit] Results
Algeco provided Jennings Building & Civil Works with 7 storage containers, on hire for 50 weeks, which were dotted up and down Mount Snowdon to provide the workers with relief from the cold, and a space to recharge and take a break.
The replacement of the pipe support structures will limit the amount of unplanned maintenance and disruptions for the Cwm Dyli hydro-electric power station.
[edit] Comment
Phil Boyes, Agent for Jennings Building & Civil Works, said: “We are really impressed that Algeco managed to find a solution lightweight enough to be transported by helicopter, but also meet our high expectations for health and safety on such an unpredictable site”.
“The site accommodation that Algeco has provided will ensure our employees have a safe place to recoup during their working day.”
Mark Fyfe, Infrastructure Business Development Manager at Algeco, said: “This was a first for Algeco. Having our units flown in by helicopter to a mountainous area is not something that we have done before, but when our customers come to us with a bespoke project, we will always do our very best to find a solution to fit their needs.
“We are pleased that Jennings Building & Civil Engineering are satisfied with our solution and we look forward to working with them again in the future.”
This article was supplied via Press Release as "Algeco supports reparations to Mount Snowdon pipeline works" along with images dated February 16, 2023.
[edit] Related articles on Designing Buildings
- Construction problems avoided by using a modular approach.
- Design for deconstruction.
- Factory-made housing.
- Flat pack.
- Modular buildings in the educational sector.
- Modular classrooms: The Friars Primary School extension.
- Off-site construction.
- Plug and play skyscrapers.
- Pod.
- Temporary and interim buildings.
- Temporary demountable structures.
- Temporary flood defences.
- Temporary services on construction sites.
- Temporary structures.
- Temporary use.
- Temporary works.
- Volumetric modular construction.
- Volumetric unit.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.